Lausanne skylight demolition 23835-25-10.25
  • 3215 Gulf Shore Blvd N
  • Naples,
  • FL
  • 34103
lausanne skylight deconstruct frame 1

Frame Demo 1

lausanne skylight deconstruct frame 2

Frame Demo 2

lausanne skylight deconstruct frame 3

Frame Demo 3

lausanne skylight deconstruct frame 4

Frame Demo 4

lausanne skylight deconstruct frame 5

Frame Demo 5

The Crew Has Been Busy with Demo Work.

While our specialists have been setting the safety anchors, the rest of the crew were busy at roof level. Caps have been removed and the acrylic lenses removed.

Detaching the frame proceeds pretty quickly.

Off with the Old.

With the framework detached and lift straps in place, the frame is lifted in one piece and moved to the ground.

Temporary Work Platform.

Another piece of the project that has been taking place simultaneously with the work above is the construction of a temporary platform. This platform, constructed of two large I-beams and plywood decking, will be used throughout the erection of the framework of the new skylight.

With the platform in place, it’s time for the construction phase.

Prepping for the next phase | On with the New.

Lausanne skylight construction 23835-15.59
In Progress | Frame pieces are being prepared for the initial assembly and lift to roof.

Careful planning has paid off and the “fun” work is about to begin!

Leave a Reply